Transcript of October 27, 2005
Citizens' General Obligation Bond
Oversight Committee Meeting
The Citizens General Obligation Bond Oversight Committee
(CGOBOC) has now discussed the Laguna Honda Hospital Replacement
Project bond financing twice, and will be discussing Laguna Honda
again at its next meeting on January 26, 2006. In a transcript
of the CGOBOCs October 27, 2005 meeting, the public learned:
- Don Condon, Interim LHH Replacement Project
Director, reported that the current budget for the LHH replacement
project is $611 million. He also reported that The
current forecasted cost of completion of the originally-planned
program of 1,200 skilled nursing beds is $620 million,
but he did not elaborate on whether the $611 million figure is
only for 780 beds, or whether the $611 million figure would be
reduced if a decision is made to eliminate building the fourth
building containing 420 beds.
- Mr. Condon reported that In 2006, we
intend to commence the remodel of the existing hospital.
This is highly unusual, because the remodel of the existing
hospital has, all along, been planned for the end of the replacement
project, sometime between 2009 and 2011. The remodel of
the existing hospital was not to have started at the beginning
of the project.
- Mr. Condon reported that the assisted living
facility on the grounds of LHH that was to be built near the
end of the replacement program still has 15 million set aside
in the budget to construct assisted living beds, but how those
assisted living beds will be used may be affected by the decision
on whether to eliminate the 420 beds if the decision is made
not to build the West Residential Tower.
- City Controller Ed Harrington reported that
the $299 million in General Obligation Bonds ... can be
used for pretty much anything on the site at Laguna Honda. It
was certainly intended for SNF [skilled nursing] beds but as
the questioning brought out a minute ago, it included some assisted
living on-site at Laguna Honda ... The discussion all along
had been that 140 assisted living beds would be built on the
campus, but Option 2 of the Controllers Where Do
We Go From Here? report to the Mayor. But various
documents currently released by the City have not pinpointed
precisely how many assisted living beds are being considered
for placement on the LHH campus.
The number of assisted living beds ranges from 375 (235 additional
assisted living beds plus the original 140), to 610 (the original
140 beds plus up to 470 additional assisted living beds). Indeed,
a Policy Recommendation Related to the Replacement of Laguna
Honda Hospital dated December 15, 2005 authored by the Mayors
advisory body known as the Long-Term Care Coordinating Council
discusses providing assistance, care and support
(not long-term care skilled nursing) to at least 1,340
people using current LHH workers.
- Mr. Harrington did not inform the CGOBOC
on October 27 that the City is now projecting to receive $820
million in tobacco settlement revenues (TSRs) over the
next 20 to 25 years during the life of the bonds. There is sufficient
money to build all 1,200 skilled nursing beds at LHH, but the
CGOBOC has not been told formally just how much in TSRs
the City expects to haul in.
- In response to a question from a CGOBOC member,
Mr. Harrington indicated that the decision to eliminate the 420
beds at Laguna Honda rests with the Health Commission, the Board
of Supervisors, and the Mayor. Mr. Harrington ignores the
fact that the citizens who approved passed of Proposition A in
1999 authorizing the sale of the replacement project bonds should
be involved in making the decision; after all, without the voters
passage of Proposition A based on promises made to them, the
other decision makers would not have the bond money
available on which to base decisions. San Francisco voters
spoke (with their ballots) in 1999 that they wanted LHH replaced
with 1,200 beds. But now those voters are being taken out
of the decision-making loop.
- Mr. Condon asserts that the fourth (West)
building can be deleted without affecting the overall design,
but this is mere hyperbole, since removing one of four buildings
completely obviously affects the overall scale of the completed
project.
- Ed Harrington continues to advocate for a
funding mechanism known as Certificates of Participation,
(COPs) a new form of bond indebtedness that voters had
not been told in 1999 would be part of the financial structure
of the replacement project. The COPs would be guaranteed
by the General Fund using a funding mechanism developed by Senator
Jackie Spier to generate and draw down a Federal revenue
stream under Medicare. The Spier bill (SB 1732) was
intended to to fund the repayment of the general obligation bonds
when used to build skilled nursing beds, but Controller
Harrington notes that [the City] could ... either put into
a revenue stream that you can then bond and use for Certificates
of Participation to build another facility at Laguna Honda, the
West building, or it could be used somewhat more flexibly in
terms of other kinds of assisted living facilities.
Indeed, rather than using the projected $120 million available
from the Spier bill to pay down the service on the bond debt,
Harrington has included that $120 million in his Option
2 to pay for construction costs of the $620
million replacement project budget, not to pay
for servicing bond indebtedness. So if the SB 1732 bill
is creatively now re-interpreted on how it can be used, does
that mean there is potentially yet another level of bait-and-switch
involved in the LHH replacement project?
- CGOBOC chairperson Pamela Jue notes that
the Committee has a responsibility and ability to look at more
than just a strict interpretation of the Committee's responsibilities.
She believes the Committee should look at capital plans
developed for the project. Hopefully, capital plans will be reviewed
during the CGOBOCs January 2006 meeting. Notably,
at the conclusion of the October 27 CGOBOC meeting, Ms. Jue asked
Deputy City Attorney Martin, the CGOBOCs advisor, whether
the Committee's jurisdiction is limited ... technically
limited [only] to Bond proceeds. Um ... if we want, and we have,
explored the tobacco settlement revenues, that we have no mandate
[to look at the TSRs] ... Mr. Martin responded that
However, to the extent that this is a General Obligation
Bond-funded project, I think you ... you do have the ability
to look into other sources and uses [of funding available] ...
I think this is a similar situation [to the Library bonds], that
you could inquire [into] and look at it as it relates to the
General Obligation Bond project [for the LHH replacement
project].
- Various documents presented to the CGOBOC
on October 27 showed a $17 million discrepancy that the LHH Replacement
Projects interim manager could not explain. The CGOBOC
has asked that a reconciliation of the discrepancy be presented
during its January 2006 meeting, because the Committee could
not ascertain how much of the project funds have been expended
to date, have been encumbered, or have not yet been encumbered.
- Ed Harrington notes that the City may avoid
... more cost escalation, but not necessarily
more cost over-runs ... on
the project, since $26 million in remaining bid packages have
not yet been completed being awarded. Mr. Condon assured
the CGOBOC on October 27 that the remaining $26 million in bid
packages should be completed by January.
- There was much discussion during the October
27 hearing about the price-per-bed at LHH having gone from $322,000
to $536,000 per bed. But Harrington neglected to tell the
CGOBOC that the $40 million project to build 106 transitional
housing beds at the Plaza Apartments that opened in mid-December
at 6th Street and Mission Street translates to $377,358 per bed.
Nobody is talking about why the initial estimate of $322,000
per skilled nursing bed at Laguna Honda was inappropriate,
at the same time they are not willing to openly discuss that
the Plaza Apartments $377,000 cost per transitional
bed is somehow appropriate. And obviously,
it is not politically correct to discuss how much in operating
costs the 106 Plaza Apartments will cost the City annually.
- Ed Harrington claims that there is not much
that can now be done to reduce the infrastructure costs at LHH
(resulting in the $536,000 per-bed amount that he calls is still
an approximate number thats decent, despite it being
an estimate developed back in May 2005 prior to the completion
of the bidding process). Indeed, Committee members were
told on October 27 that more infrastructure has been placed on
order than is required to support a 780-bed rebuild project,
because the decision to eliminate the additional 420 beds had
not yet been made. Mr. Harrington now claims that the Link Building
contains much of the infrastructure for the entire campus, but
this stands in stark contrast to testimony presented by the initial
Replacement Project manager, Michael Lane, who informed the Health
Commission on March 15, 2005 that the reason the East Building
had been kept in the scaled-back 780-bed configuration was because
the East Building contained much of the telecommunications, generators,
and other infrastructure for the campus.
Notably, Harrington said on October 27 that trying to cut back
on infrastructure would have required reengineering,
but, indeed, the various rounds of bidding had been designed
to encourage value [re]engineering by bidders. Harrington
must have hoped that the CGOBOC members would not remember that
value engineering had been a principal goal of the bidding process.
Nor did Harrington specify that one of the value engineering
recommendations adopted is to reduce the height of ceilings in
the replacement project to a mere eight feet.
- Typically, value engineering is performed
at the start of building projects, not at the stage of issuing
bids for the work. But none of the CGOBOC members asked
why value engineering had not been performed at the outset during
initial design of the LHH Replacement Project, and none of Committee
members followed up on the loss of value engineering savings
between Bid Round 1 and Bid Round 2. Don Condon reported that
the second round of bids reduced the construction costs by $5.5
million, but none of the CGOBOC members inquired about how much
the first round of bids had reduced construction. To her
credit, Committee Chairperson Jue asked would we have better
off if we had accepted the previous [first] round of bids?,
and Don Condon responded Thats possible.
- Ed Harrington noted on October 27 that without
the first $90 to $100 million in available TSRs
... you don't have the funds to complete the skilled nursing
facility beds. This is preposterous, because the
Health Commission has previously been told that the cost per
floor for the residential skilled nursing beds is only $7 million
per floor, each floor having 60 beds. At seven floors, building
the 420 beds would only cost $49 million, not $100 million. Even
if the $7 million per floor estimate had escalated by 34 percent,
which is the claimed cost over-run, rather than needing $49 million
for the 420 beds, the City would need only $65.66 million ($49
million plus $16.66 million), not $90 to $100 million, but Harrington
does not mention why an extra $35 million would be needed to
complete the skilled nursing beds. Because the City is
projected to earn $820 million in TSRs, the City has the
money to complete the full 1,200-bed rebuild of Laguna Honda
Hospital.
Various members of the public including
Sister Miriam Walsh, Virginia Leishman, and Patrick Monette-Shaw
presented oral testimony during the public comments section
of this meeting.
Top
_______
Copyright (c) 2005 by Committee to Save LHH. All rights
reserved. This work may not be reposted anywhere on the
Web, or reprinted in any print media, without express written
permission. E-mail the Committee
to Save LHH.